WINONA LAKE, INDIANA  46590

 

1998 SANITARY AND SEWER

PROJECT SCHEDULE


ALL PROJECTS AND DATE ARE SUBJECT TO CHANGE!


REVISED 3-10-98

PROJECT NAME                                            FINISH DATE   STATUS

1.  SANITARY SEWER MAP   980002.02

             A. Drafting...............................................................04/11/98 R............ IP

2.  STORM SEWER MAP   980002.03

A. Preliminary (with existing data)

                                                        1. Drafting................................................02/05/98.................C

                                                        2. Copies..................................................02/09/98..................C

                                                        3. Present to Town Council...................02/10/98..................C

B. Final (with field data)

                                                        1. Field Survey........................................06/11/98..................IP

                                                        2. Drafting................................................08/01/98..................IP

                                                       3. Present to Town Council....................08/11/98

 

3.  SUNDAY LANE SANITARY SEWER   970002.06

                                        A. Field Survey.......................................................01/29/98

                                        B. Design and Drafting..........................................03/24/98 R

                                        C. Bid Opening........................................................04/14/98 R

                                        D. Award..................................................................04/2 8/98 R

                                        E. Start Construction..............................................05/12/98 R

 

4.  GRACE AVENUE   980002.04

                                        A. Utility Location..................................................01/28/98

                                        B. Field Survey........................................................01/30/98

                                        C. Design and Drafting...........................................03/24/98 R

                                        D. Bid Opening........................................................04/28/98 R

                                        E. Award...................................................................05/12/98-R

                                        F. Start Construction..............................................05/26/98 R

 

                    5.   PARK AVENUE # 1 (KING'S HIGHWAY INT. TO OLD HOTEL)   980002.05

                                        A. Utility Location..................................................02/05/98

                                        B. Field Survey........................................................02/13/98

                                        C. Design and Drafting...........................................03/24/98

                                        D. Bid Opening........................................................04/14/98

                                        E. Award...................................................................05/12/98

 

   6.  ROY STREET STORM DRAIN   980002.06

                                        A. Utility Location..................................................04/03/98

                                        B. Field Survey........................................................04/14/98

                                        C. Design and Drafting..........................................05/15/98

D.  Start Construction (in-house)

 

        7.  ROBSON ROAD SANITARY SEWER    980002.07

                                        A.   Utility Location...............................................07/07/98

                                        B.   Field Survey.....................................................07/28/98

                                        C.   Design and Drafting.......................................09/22/98

                                        D.   Bid Opening....................................................01/26/99

                                        E.   Award...............................................................02/09/99

                                        F. Start Construction............................................03/23/99

 

            8.  BOYS CITY SANITARY SEWER   980002.08

                                        A.   Utility Location..............................................07/08/98

                                        B.   Field Survey....................................................07/17/98

                                        C.   Design and Drafting......................................09/22/98

                                        D.   Bid Opening...................................................10/27/98

                                        E.   Award..............................................................11/10/98

                                        F.   Start Construction..........................................11/24/98

 

            9.  MAPLE STREET (NO DESIGN, AS-BUILT DRAWING ONLY)    980002.09

            A.  Field Survey......................................................11/17/98

             B.   Drafting.............................................................12/11/98

 

10.  13TH & 14TH SANITARY SEWER   970002.07

                                        A.   Utility Location...............................................11/05/98

                                        B.   Field Survey.....................................................11/13/98

                                        C.   Design and Drafting........................................12/22/98

                                        D.   Bid Opening.....................................................02/09/99

                                        E.   Award................................................................02/23/99

                                        F.   Start Construction...........................................03/23/99

 

                    11. SCHOOL STREET (NO DESIGN-AS-BUILT DRAWING ONLY)   970002.10

A.  Field Survey

              B.   Drafting............................................................09/01/98

Note: 1. This Project Schedule includes design, bidding, contract award, and contract signing. The Schedule excludes actual construction times.

2. Projects #6 & #9 will be constructed in-house, therefore, no bidding and award activities are scheduled.


LEGEND        C= COMPLETE          R= REVISED          IP= IN PROGRESS