1998 SANITARY AND SEWER
PROJECT SCHEDULE
PROJECT NAME FINISH DATE STATUS
1. SANITARY SEWER MAP 980002.02
A. Drafting...............................................................04/11/98 R............ IP
2. STORM SEWER MAP 980002.03
A. Preliminary (with existing data)
1. Drafting................................................02/05/98.................C
2. Copies..................................................02/09/98..................C
3. Present to Town Council...................02/10/98..................C
B. Final (with field data)
1. Field Survey........................................06/11/98..................IP
2. Drafting................................................08/01/98..................IP
3. Present to Town Council....................08/11/98
3. SUNDAY LANE SANITARY SEWER 970002.06
A. Field Survey.......................................................01/29/98
B. Design and Drafting..........................................03/24/98 R
C. Bid Opening........................................................04/14/98 R
D. Award..................................................................04/2 8/98 R
E. Start Construction..............................................05/12/98 R
4. GRACE AVENUE 980002.04
A. Utility Location..................................................01/28/98
B. Field Survey........................................................01/30/98
C. Design and Drafting...........................................03/24/98 R
D. Bid Opening........................................................04/28/98 R
E. Award...................................................................05/12/98-R
F. Start Construction..............................................05/26/98 R
5. PARK AVENUE # 1 (KING'S HIGHWAY INT. TO OLD HOTEL) 980002.05
A. Utility Location..................................................02/05/98
B. Field Survey........................................................02/13/98
C. Design and Drafting...........................................03/24/98
D. Bid Opening........................................................04/14/98
E. Award...................................................................05/12/98
6. ROY STREET STORM DRAIN 980002.06
A. Utility Location..................................................04/03/98
B. Field Survey........................................................04/14/98
C. Design and Drafting..........................................05/15/98
D. Start Construction (in-house)
7. ROBSON ROAD SANITARY SEWER 980002.07
A. Utility Location...............................................07/07/98
B. Field Survey.....................................................07/28/98
C. Design and Drafting.......................................09/22/98
D. Bid Opening....................................................01/26/99
E. Award...............................................................02/09/99
F. Start Construction............................................03/23/99
8. BOYS CITY SANITARY SEWER 980002.08
A. Utility Location..............................................07/08/98
B. Field Survey....................................................07/17/98
C. Design and Drafting......................................09/22/98
D. Bid Opening...................................................10/27/98
E. Award..............................................................11/10/98
F. Start Construction..........................................11/24/98
9. MAPLE STREET (NO DESIGN, AS-BUILT DRAWING ONLY) 980002.09
A. Field Survey......................................................11/17/98
B. Drafting.............................................................12/11/98
10. 13TH & 14TH SANITARY SEWER 970002.07
A. Utility Location...............................................11/05/98
B. Field Survey.....................................................11/13/98
C. Design and Drafting........................................12/22/98
D. Bid Opening.....................................................02/09/99
E. Award................................................................02/23/99
F. Start Construction...........................................03/23/99
11. SCHOOL STREET (NO DESIGN-AS-BUILT DRAWING ONLY) 970002.10
A. Field Survey
B. Drafting............................................................09/01/98
Note: 1. This Project Schedule includes design, bidding, contract award, and contract signing. The Schedule excludes actual construction times.
2. Projects #6 & #9 will be constructed in-house, therefore, no bidding and award activities are scheduled.
LEGEND C= COMPLETE R= REVISED IP= IN PROGRESS